Supreme Court lets White House continue construction on $400 million ballroom

Supreme Court lets White House continue construction on $400 million ballroom


Supreme Court lets White House continue construction on $400 million ballroom

WASHINGTON— A divided Supreme Court on Monday allowed the White House to continue construction on a $400 million ballroom project as lawsuits play out, a win for President Donald Trump.

The apparent 5-4 decision replaces a temporary order issued earlier this month, shortly before a court-ordered halt would have gone into effect.

That temporary order was signed by Chief Justice John Roberts, assigned to handle appeals from the capital. But he publicly disagreed with the latest decision, writing a strong dissent that said the project is likely unlawful because it hasn't been approved by Congress.

“Today’s decision is no victory for the separation of powers,” Roberts wrote. The court’s three liberal-leaning justices agreed.

The majority, on the other hand, found the National Trust for Historic Preservation likely did not have the legal right to challenge the project.

The unsigned order pointed to government arguments that the ballroom would address national security concerns by shielding a planned underground military installation and offering a more secure structure for large events than the tents currently used.

By contrast, “the only harm the Trust claims is the offense one of its members will suffer from having to view a structure of the ‘scale,’ ‘height,’ and ‘massing’ the government intends,” it states.

Trump applauded the decision, writing in a social media post, “I am pleased to report that the United States Supreme Court has just ruled in favor of the Ballroom/Military Complex being built without any further contingency, doubt, or threat.”

The majority's order did not directly decide the legality of the project, and the suit will return to lower courts. Documents filed in the case, though, say that key portions of the project could be complete within months — a quick timeline compared with a typical legal case.